The initial step was taken in the works for the 2020 - 2021 harvest.
 

There are two ongoing projects:

 

1. In partnership with Pinhalense, an expansion will be carried out on line 1 of production, where a new set of silos will be installed, which will serve as a lung in production. In addition to preventing machinery stoppages, the new investment is expected to increase production by around 20,000 bags per month, in addition to avoiding extra work by forklift operators and warehouse assistants.
 
2. Due to the increase in shipments with alphabags, and in order to make the procedure more agile, docks will be built for this loading modality.
 
The civil construction and assembly schedule is expected to end in July and August 2020.